Burial of the Horns Rev 3 Export Cable completed in 12 days
On the 22nd of June JD-Contractor A/S completed the burial of the entire length of the 33 km Horns Rev 3 Export Cable. From the beach 1.5 km North of Henne Strand to the offshore transformer platform at Horns Rev. The total burial campaign was completed in just 12 days - 9 days of operation and 3 days of standby, waiting on weather.